DANNY SETIAWAN (2014) ANALISIS PERCEPATAN WAKTU PROYEK DENGAN TAMBAHAN BIAYA YANG OPTIMUM. S1 thesis, Universitas Muhammadiyah Yogyakarta.
Text (Halaman Judul)
Halaman Judul.pdf
Download (236kB)
Halaman Judul.pdf
Download (236kB)
Text (Bab I)
Bab I.pdf
Download (22kB)
Bab I.pdf
Download (22kB)
Text (Bab II)
Bab II.pdf
Restricted to Registered users only
Download (24kB)
Bab II.pdf
Restricted to Registered users only
Download (24kB)
Text (Bab III)
Bab III.pdf
Restricted to Registered users only
Download (1MB)
Bab III.pdf
Restricted to Registered users only
Download (1MB)
Text (Bab IV)
Bab IV.pdf
Restricted to Registered users only
Download (28kB)
Bab IV.pdf
Restricted to Registered users only
Download (28kB)
Text (Bab V)
Bab V.pdf
Restricted to Registered users only
Download (9kB)
Bab V.pdf
Restricted to Registered users only
Download (9kB)
Text (Bab V)
Bab V.pdf
Restricted to Registered users only
Download (2MB)
Bab V.pdf
Restricted to Registered users only
Download (2MB)
Text (Naskah Publikasi)
Naskah Publikasi.pdf
Download (1MB)
Naskah Publikasi.pdf
Download (1MB)
Abstract
Hasil penelitian ini menunjukan bahwa (1) Biaya proyek pada saatkondisi normal tanpa penambahan jam lembur diperoleh sebesar Rp. 1.079.356.295,00 dengan durasi117 hari. dengan penambahan 4 jam kerja makawktu proyek berkembang menjadi 100,15 hsri dan penambahan biaya sebesar Rp. 96.844.892,00menjadi sebesar Rp. 1.176.201,00. 2.Biaya dan waktu yang optimal setelah dilakukan penambahan jam kerja adalah pada saat penabahan 1 jam kerja yaitu pada durasi 109,48 hari dengan biaya total sebesar Rp. 1.301.077.370,95
Item Type: | Thesis (S1) |
---|---|
Uncontrolled Keywords: | MICROSOFT PROJECT - DATA PROYEK - WAKTU AN BIAYA |
Divisions: | Fakultas Teknik > Teknik Sipil S1 |
Depositing User: | Unnamed user with email robi@umy.ac.id |
Date Deposited: | 21 Jun 2022 06:28 |
Last Modified: | 21 Jun 2022 06:28 |
URI: | https://etd.umy.ac.id/id/eprint/15683 |