ANALISIS PERCEPATAN WAKTU PROYEK DENGAN TAMBAHAN BIAYA YANG OPTIMUM

DANNY SETIAWAN (2014) ANALISIS PERCEPATAN WAKTU PROYEK DENGAN TAMBAHAN BIAYA YANG OPTIMUM. S1 thesis, Universitas Muhammadiyah Yogyakarta.

[thumbnail of Halaman Judul] Text (Halaman Judul)
Halaman Judul.pdf

Download (236kB)
[thumbnail of Bab I] Text (Bab I)
Bab I.pdf

Download (22kB)
[thumbnail of Bab II] Text (Bab II)
Bab II.pdf
Restricted to Registered users only

Download (24kB)
[thumbnail of Bab III] Text (Bab III)
Bab III.pdf
Restricted to Registered users only

Download (1MB)
[thumbnail of Bab IV] Text (Bab IV)
Bab IV.pdf
Restricted to Registered users only

Download (28kB)
[thumbnail of Bab V] Text (Bab V)
Bab V.pdf
Restricted to Registered users only

Download (9kB)
[thumbnail of Bab V] Text (Bab V)
Bab V.pdf
Restricted to Registered users only

Download (2MB)
[thumbnail of Naskah Publikasi] Text (Naskah Publikasi)
Naskah Publikasi.pdf

Download (1MB)

Abstract

Hasil penelitian ini menunjukan bahwa (1) Biaya proyek pada saatkondisi normal tanpa penambahan jam lembur diperoleh sebesar Rp. 1.079.356.295,00 dengan durasi117 hari. dengan penambahan 4 jam kerja makawktu proyek berkembang menjadi 100,15 hsri dan penambahan biaya sebesar Rp. 96.844.892,00menjadi sebesar Rp. 1.176.201,00. 2.Biaya dan waktu yang optimal setelah dilakukan penambahan jam kerja adalah pada saat penabahan 1 jam kerja yaitu pada durasi 109,48 hari dengan biaya total sebesar Rp. 1.301.077.370,95

Item Type: Thesis (S1)
Uncontrolled Keywords: MICROSOFT PROJECT - DATA PROYEK - WAKTU AN BIAYA
Divisions: Fakultas Teknik > Teknik Sipil S1
Depositing User: Unnamed user with email robi@umy.ac.id
Date Deposited: 21 Jun 2022 06:28
Last Modified: 21 Jun 2022 06:28
URI: https://etd.umy.ac.id/id/eprint/15683

Actions (login required)

View Item
View Item